This report is based on public company disclosures, filings and announcements reviewed by GSN; figures are as stated by the company and have not been independently verified.

Eco Wave Power Global AB (publ) (Nasdaq: WAVE), the Sweden-registered onshore wave energy company, said on September 22, 2026 that its founder and chief executive, Inna Braverman, will speak at the inaugural Futures: Ocean Forum in Newport, Rhode Island on September 24, and will use the visit to tour two sites and meet state and local officials about what the company calls a potential first commercial wave energy project in the state. The announcement was furnished to the U.S. Securities and Exchange Commission as an exhibit to a Form 6-K.

The company said the invitation followed Braverman’s engagement with Rhode Island’s Secretary of Commerce, Stefan Pryor, and Jason Dodier, the state commerce agency’s chief business development officer. Governor Dan McKee is scheduled to attend the forum. The Rhode Island interest, the company said, rests on a feasibility study it carried out with Shell Marine Renewable Energy, which evaluated potential locations along the U.S. coastline and found sites in Rhode Island “among the locations considered particularly suitable” for the company’s onshore technology.

Eco Wave Power’s system mounts floaters on existing coastal structures such as breakwaters, jetties and piers, and converts wave motion into electricity close to shore. Its first U.S. installation is a pilot at the Port of Los Angeles, built with Shell Marine Renewable Energy and AltaSea. Braverman said in the release that the ocean’s potential as a clean energy source is largely untapped and that electricity demand from artificial intelligence and data centres creates an opportunity for wave energy.

Reading the filing

What is disclosed is a speaking slot, a site visit and meetings. What is not disclosed is any of the things that make an energy project real: an agreement with the state or a site owner, a named site, a capacity in megawatts, a cost, a buyer for the power, a permit application, or a date for any of them. The words the filing uses are “potential,” “evaluate,” “explore” and “could become.”

The Shell study is presented as the reason Rhode Island is on the list, but the filing does not say whether the study is public, what criteria it applied, how many sites it ranked, or whether Shell has any continuing role in a Rhode Island project. The only U.S. deployment the filing names is the Los Angeles pilot, and it gives no output or performance data for that pilot.

Government interest and a contract are different things. A state commerce agency’s invitation and a governor’s attendance at a forum are engagement. In the United States, the steps that create obligations for a shoreline energy project are control of the site, an application to connect to the grid, federal and state permits for structures on the coast and in the water, and an agreement with someone to buy the power. None is mentioned.

The data centre argument is the chief executive’s framing, given without figures. Onshore wave energy at the scale of a pier or breakwater installation is a different order of magnitude from the load of a data centre campus, and the filing does not attempt to connect the two with numbers.

Questions worth asking

Which two sites, and who owns them? Onshore wave energy needs an existing breakwater, jetty or pier, so the owner, whether a port authority, the Navy, a municipality or the state, is the party whose consent matters.

What capacity did the Shell study contemplate for a Rhode Island site? The filing gives none.

Who would buy the power, and at what price? No offtake or power purchase arrangement is mentioned, and without one a project has no revenue.

What has the Los Angeles pilot produced? It is the company’s first U.S. installation and the only operating reference the filing offers; the filing gives no data on it.

Key terms in this story

Form 6-K. The form a foreign company listed in the United States uses to furnish material it publishes at home, including press releases. Furnishing a release on a 6-K does not add to or vouch for its content.

Onshore wave energy. Systems that sit on existing coastal structures and capture wave motion at the shoreline, as opposed to offshore devices moored in open water. The company’s case for the approach is lower installation and maintenance cost and proximity to demand.

Feasibility study. An analysis of whether a project is technically and economically workable, typically covering site conditions, permitting and economics. It precedes, and does not replace, site agreements and permits.

Offtake agreement. A contract under which a buyer commits to purchase a project’s output on set terms. Lenders to energy projects generally require one before financing construction.

What to watch

September 24, 2026: the Futures: Ocean Forum in Newport, and the company’s planned site visits and meetings with state and local officials during the trip.

The filing gives no timetable for a development agreement, a permit application or project financing in Rhode Island.